Where Davao Light Customer's stand, as of August 2017, System's loss charges are lower than the ERC mandated Cap of 8.5 %. Attend the Public Consultation at Pinnacle Hotel Tomorrow August 31, 2017 at 9AM

JAN FEB MAR APR MAY JUNE JULY AUG Davao  Light 2017 residential 9.0735 8.7800 9.2683 9.9411 9.3652 9.3063 9.2152 9.4962 residential system loss charges : Sys. Loss Charge 0.252 0.2335 0.2554 0.3838 0.3428 0.3445 0.3349 0.3497 Generation & Trans. 4.9001 5.0248 5.4253 5.869 5.3805 5.3375 5.2337 5.4142 System Loss %age 0.0514 0.0465 0.0471 0.0654 0.0637 0.0645 0.0640 0.0646 Mandated Cap 0.085 0.085 0.085 0.085 0.085 0.085 0.085 0.085 sec. retail 9.0712 8.8260 9.2680 9.9324 9.2903 9....

WHY I WILL SUPPORT THE APPLICATION ON THE POWER SUPPLY CONTRACT BETWEEN DLPC AND SAN MIGUEL CONSOLIDATED POWER

WHY I WILL SUPPORT THE POWER SUPPLY CONTRACT   BETWEEN  DAVAO LIGHT AND SAN  MIGUEL CONSOLIDATED POWER CORPORATION  SAN MIGUEL CONSOLIDATED POWER CORPORATION’S RATE SCHEDULE BELOW Demand Charge at Php 1,770.61 per KW, and Energy Charges per kwh at Php 1.9397 * * Indicative charges per Sec 9.4 of the application. Contract Period  10 years Reference : Application under ERC CASE # 2017-029RC COMPARES with THERMA SOUTH INC’s EXISITING RATE SCHEDULE BELOW Demand   KW at Php  2,333.95 per KW.  Contract period = 25 years Reference : ERC Decision on ERC CASE # 2013-021RC Yes, we are shouldering the difference of Php 563.34 / KW in Total Demand Charges based on the above-mentioned ERC documents. This translates to a difference of Php 0.7824 per kwh, a substantial reduction Both power plants source their coal from the same supplier / place in Kalimantan, Indonesia so the fuel costs are assumed to be the ...

ECONOMIC DISPATCH OF POWER PLANT CAPACITY AS UPDATED

ECONOMIC DISPATCH OF POWER PLANT CAPACITY There are three basic types of plants in a given GRID :  Baseload Power Plants =  These power plant compose the bulk of the capacity available to supply the given grid with continuous power for a minimum of 16 hours a day.  The Department of Energy is setting 70 percent of the Grid Capacity as Baseload Capacity. From the economic standpoint, the baseload plant have inherent high capital cost per KW, but with minimal fuel cost, if at all eg. Hydro Power Plants., Geothermal Power Plants, Natural Gas, Coal-fired Power Plants are best examples of existing power plants in operation.  Thermal or Bunker-C  Fuel-fed power plants which have efficient heat rates are no longer considered as Baseload power plants for the Main Grid considering the highest fuel cost they incur at Php 8.50 / Kwh.  They are considered at baseload plants for island-grid or off-grid areas. Mid-Merit Power Plants =  These pow...

DRAFT EXECUTIVE ORDER / ACT / ORDINANCE / BILL ON THE RATIONALIZATION OF POWER GENERATION IN THE REPUBLIC OF THE PHILIPPINES

DRAFT EXECUTIVE ORDER / ACT / ORDINANCE /  BILL ON THE RATIONALIZATION OF POWER GENERATION IN THE REPUBLIC OF THE PHILIPPINES WHEREAS  The country is now crossing the Rubicon as far as the electric power industry is concerned, with the Luzon Grid having a more or less stable and balanced Power Generation Mix and the Visayas Grid still having power shortages despite being interconnected with the Luzon Grid, and the Mindanao Grid having an abnormal Glut of more than 100 percent of Peak Demand requirement. WHEREAS  There is an abnormal situation in the Mindanao Grid, with most of the Grid connected power plants running at 50 % capacity factor, and the Hydro Power plants down to 35 to 40 % capacity factor, resulting into spilling or wasted water. WHEREAS   There is a constant danger to lives and properties if the Hydro Power Plants are not operated as designed, and other plants similarly situated face the same prospect of being physically impaired...